MATH3250 · Theorem · Chapter 8 · Algorithm design
The greedy schedule stays ahead
1 steps of prerequisites below it
For any feasible schedule a₁, …, a_l in chronological order, the greedy schedule has an i-th request finishing no later than a_i for every i ≤ l, so it has at least l requests.
Taught in
- 8.1 Greedy choice, exchange and interval scheduling · introduced
Uses
- Ordinary and strong induction · used in its proof, proof step 8.1
- Positive-length half-open requests · used in its proof, proof step 8.1
Used by
No later knowledge point in these notes uses it.
Everything this builds on, earliest first · 2 steps
Each step comes after its own prerequisites, so reading in this order never needs something you have not met. It is a reading order for these notes, not a diagnosis of what you know.
Possible roots and a review route need your own answers on these points. None are recorded yet, so none are suggested.
Longest chain down to a starting point
Each step is used by the one above it, across courses where the notes link them. It ends at a point the notes define without another point.