CSCI2740 · Definition · Chapter 7 · Weighted interval scheduling
Predecessor index
0 steps of prerequisites below it
For activities numbered in nondecreasing finish order, the predecessor index p(i) is the largest j < i with f_j ≤ s_i, or 0 if there is none.
Taught in
- 7.1 Weighted interval scheduling · introduced
Builds on
Nothing in the notes sits below this point: it is a starting point.
Used by
Possible roots and a review route need your own answers on these points. None are recorded yet, so none are suggested.
Longest chain down to a starting point
Nothing is recorded below this point: it is a starting point.